Airport Expansion Flies with PreCast Pipe
by Paul M. Heffern, PE., Corporate Engineer Independent Concrete Pipe
Co., Sylvania, Ohio
A $600 million expansion and modernization project at the
Louisville International Airport relied on the strength and dependability
of precast
reinforced concrete pipe as a critical component of the new facility.
In the trench, alignment of the 108-inch RCP included four curves
totaling 1,580 feet.
Situated
within 500 miles of nearly 50 percent of the nation's consumer markets,
Louisville, KY., is a growing city and major commerce center in the Southeast
and Midwest. To ensure continued growth and prosperity, efficient and effective
air service was clear. A substantial portion of Louisville's economic vitality
stems from the United Parcel Service, which has made the airport its hub
for international shipments. UPS employs more than 14,000 people there
- a number expected to increase to 27,000 by 2010. Louisville International,
located just six miles from the city's central business district, is a
world renowned cargo hub. In 1995,
it handled close to 3 billion pounds of cargo making it the fourth-busiest
cargo airport in the country and the sixth-busiest in the world.
The airport
expansion project was initiated in 1988 by the community and the airport's
owner and operator, the Regional Airport Authority of Louisville and Jefferson
County (RAA). The centerpiece of the project are two new parallel runways.
One runway, measuring 7,775 feet, is located on the airport's east side
and was completed
in the fall of 1995. The second and most recent project is located on the
airport's west side and measures 10,000 feet. The new project also
included associated
taxiways and aprons.
These new surfaces, when combined with the 3,000-acre facility,
drastically increased the airport's rainfall runoff. The new facility depended
on a closed drainage system capable of handling discharge of more than 1,200
cubic feet per second at the outlet end.
In the original plan for the west runway, the primary storm
interceptor was designed to consist of single, double and triple lines
of 10' x 5' and 12' x 5' cast-inplace boxes. However, prior to bid-letting,
the Kentucky division of Independent Concrete Pipe Company, an American
Concrete Pipe Association member, presented an alternative plan based on
the use of specially designed 108-inch and 96-inch precast reinforced concrete
pipe.
A triple line of 108-inch RCP was used with as many as 50 pieces of 8-foot length pipe installed in a single day.
It's not just about doing it right, it is about doing it right and on-time.
Independent
Concrete's General Manager Mike Pepper and Corporate Engineer Paul Heffern
met with Robert A. Brown, RAA's Director of Engineering, and local design
firm Howard Needles Tamman & Bergendoff's Project Design Engineer,
Daniel E. Beyke, and engineer, Todd Tabor, to detail the two major advantages
to their plan.
Heffern and Pepper, in a direct comparison of precast concrete pipe to
cast-in-place box, showed that using precast concrete pipe would provide
an immediate savings
of several million dollars. Equally as important was the ability to meet the
project's tight production schedule, in part because UPS contributed $1
million to help get the runway open prior to the carrier's peak 1997 Christmas
season. Independent Concrete was able to prove that precast concrete pipe would
expedite the project's completion date significantly.
Independent Concrete's plan to use precast reinforced concrete pipe won
out over cast-in-place boxes with an installed savings of $3.4 million. The airport
authority awarded the contract to MAC Construction & Excavating Inc. of New
Albany, Ind., which submitted the low bid of $10.2 million out of four bidding
contractors. The project's completion date was set for October 30, 1997.
Working closely Independent Concrete with HNT&B engineers, and airport
authority engineers revised the plan to include roughly 13,300 linear feet
of precast pipe. The plan included 11,440 linear feet of 108-inch diameter
RCP and 1,550 linear feet of 96-inch RCP in eight-foot segments.
A key selling point of the plan was the commitment by all parties to adhere
to an aggressive installation schedule. To assure adequate productivity,
Independent Concrete formed a joint venture with CSR Hydro Conduit, in Louisville,
for production of the 96inch RCP. Art Cannon, sales manager for CSR
Hydro Conduit, coordinated production of the 96-inch pipe.
The 108-inch pipe was produced in Independent Concrete's McCracken VIERa-MAC
Dry Cast Machine at the company's Louisville plant.
The pipe was specially designed for the installed conditions of loading
and bedding using the American Association of State Highway and Transportation
Officials (AASHTO) Standard Specifications for Highway Bridges, Section
17, "Soil-Reinforced
Concrete Structure Interaction Systems." The pipe was designed to
accommodate a 1 million pound aircraft loading in case future expansion
placed a new taxiway over or near the drainage pipe. PIPECAR, design software
developed by Simpson Gumpertz & Heger Inc. in cooperation with the
Federal Highway Administration and the ACPA, was used in this phase of
the project. PIPECAR was used to design for installed conditions of loading
and bedding rather than the indirect design method. "The PIPECAR
software provides a computerized method to perform structural analysis
and reinforcing design of
concrete pipe." Heffern said. "This allows the user to obtain
reinforcing steel areas for specified pipe geometry, material properties
and loading data."
A
dump truck bed equipped with an air controlled gate was used to control
placement of the bedding material, #57 crushed stone.
Inlet
structures were formed and cast-inplace by MAC Construction.
Single
line of 108-inch RCP on straight alignment.
In
order to evaluate the million-pound aircraft live load on the pipe, the
load distribution through the 17inch thick
concrete pavement and backfill was based on the load distribution analysis
presented in Design Data #15, "Aircraft Loads" published by the
ACPA. Load Analysis and Structural Designs were performed at 21 locations
along the 96-inch and 108-inch diameter pipe alignment to determine the
most critical combination of live and earth load. All pipe was manufactured
in accordance with ASTM Standard c76 with ASTM C443 joints
utilizing oil resistant gaskets. Steel reinforcement cage configurations
were full, circular inner and outer cages with quadrant mats - with and
without stirrups at the pipe invert.

The
outlet end of the triple 108-inch line shows the bedding and baclifill
as detailed in Figure G.
To stay within the tight production schedule, Independent Concrete's
Plant Manager Sonny Gollar and General Manager Pepper established a demanding
work schedule beginning at 4 a.m. and often not ending until 5:30 p.m. To assure the production
schedule could be met and enable the manufacture of a closetolerance
joint, new joint ring forms were ordered. After receiving the new forms,
as many as 24 pieces of 108-inch pipe were manufactured per day, using
only 12 sets of rings.
"We would cure the day's early production so it could be handled,
then we recycled the pallets and headers and used them again that same
day" Pepper
said.
Independent Concrete was able to adhere to that schedule because
of the versatility of the VIBRO-MAC equipment, he said. A large hydraulic
pipe tipper was used to pick up each finished pipe after three or four
hours of curing, and then the pallet was pulled off. The pipe was set down,
the header was removed with a bridge crane and the joint-forming rings
were used again.
"It just goes to show you that you can make more pipe than you have pallets
and headers for in a day with this type of equipment." Pepper said.
Once the construction phase was underway, Independent Concrete was able
to ship as many as 59 pieces of 108-inch pipe per day to the job site under
the supervision of Scott Holzapfel, Independent Concrete's Transportation
Manager. In the
trench, alignment of the 108-inch pieces included four curves totaling
1,580 feet. In order to fit these curves, special radius pipe
was manufactured with a 3 1/2-inch bevel at the spigot ends.
"We had to maintain tight quality control in order for the radii
pipe to layout correctly." Pepper said.
The project also set a precedent for MAC Construction. "This is the
largest pipe the company has ever installed." said Dennis Coffman,
MAC's Vice President of Construction. The installation was led by Steve
Stinnett, project manager, and Ed Calvert, project superintendent.
While MAC Construction was installing the 108-inch storm sewer, the Harper
Company of Hebron, Ky., was in the midst of a separate but related $30
million project to place more than 600,000 tons of concrete pavement and
aggregate base courses for the runway, taxiways and roadways. Harper's
runway paving project also included more than 23,700 feet of RCP, manufactured
by CSR Hydro Conduit and Independent Concrete Pipe, ranging from 18-inch
to 108-inch diameter for related drainage facilities.
In addition, Gohmann Asphalt, of Clarksville, Ind., was
completing construction of ramps and sitework for UPS, which included more
than 14,000 feet of l2-inch to 72-inch diameter RCP.
Independent Concrete shipped the last of the 108-inch pipe in mid-October
and the installation phase for the big pipe concluded at the end of that
month. The project was completed on schedule and under budget and the new
runway is currently being used, enabling simultaneous takeoffs and landings,
doubling the airport's capacity. "The success of the project relied
on the hard work and expertise the numerous participants brought to the job." said
Barry Bundrant, Independent Concrete's President. "This project will
have a positive impact on the growth and prosperity of the city of Louisville
for many years to come."